close window

Victor Jerome Glover

 Total EVAs:  4
 Total EVA time:  26h 07m

No. Date Together with Time Main tasks and notes
 1  27.01.2021  M. Hopkins  6h 56m
This spacewalk focused on completing cable and antenna rigging for the "Bartolomeo" science payloads platform outside the ESA Columbus module. The duo also configured a Ka-band terminal, known as COL-Ka.
 2  01.02.2021  M. Hopkins  5h 20m
Main tasks were the installation of a final lithium-ion battery adapter plate on the port 4 (P4) truss that wrapped up battery replacement work begun in January 2017.
 3  28.02.2021  K. Rubins  7h 04m
They began assembling and installing modification kits required for upcoming solar array upgrades.
 4  13.03.2021  M. Hopkins  6h 47m
They vent and relocated ammonia jumper cables, installed a structural "stiffener" on the airlock thermal cover, and completed the connection of payload cables on the new Bartolomeo platform on the Columbus module.